Sri Krishna Haveli project update – Bhaktivedanta Manor.
Construction work on Bhaktivedanta Manor’s new Haveli has begun and is in full swing with a date of completion
for Janmashtami 2019.
• Secondary steel work complete
• Waterproofing complete
• Pumping station installed
• Underground attenuation tank complete
• Brick work started
• Playground design/user consultation running
Works have also started on the
• Electrical substation
• Ladies ashram
• Roof and first floor slabs
• Base course around building
• Timber work