Shree Krishna Haveli project update – Bhaktivedanta Manor – UK.
We are very pleased to say that construction is moving forward with great momentum. Any time lost due to unforeseeable conditions is being made up by working late and over the weekends. Works now completed include the first fix of all electrical and mechanical, kitchen fridges and freezers, the windows and external doors, screeding, ridge tiles on roof. With restoring the cottage building (ladies ashram) it was found that the old roof beams could not be saved due to rot, so a new roof is now being manufactured. Externally the hard landscaping has begun but due to the Janmashtami festival some of the work will be held back to save on public inconvenience. A huge thank you goes to those working hard to complete on time (October/ November), to all those still raising funds, and to all of you for tolerating the present inconveniences due to construction.